Urban Hydraulic Engineering

WVA Klagenfurt BA10

All measures planned in construction phase 10 of the Klagenfurt waste incineration plant serve to ensure the supply of drinking-, process- and fire-fighting water. Pipeline rehabilitation and new installations are carried out by using conventional open trench methods, and innovative trenchless rehabilitation options. Among other things, this project was initiated because of the expansion of the supply network in the supply areas, and the adaptation to the state of the art of the WVA.

Details

Client: STW Klagenfurt AG
Net Manufacturing Cost: € 1,8 Mio.
Planning Period: 2016
Execution Period: 2017–2020
Scope of Activities: Preliminary planning, submission planning, submission, implementation planning, applications for subsidies, local construction supervision, final review under water law, collauditing etc.